Construction contractBali: 10 red flagsto fix before you sign

The ten clauses that cause most trouble in the standard construction contract that Bali builders send, from vague scope to front-loaded payments, and the wording to ask for instead before you sign.

27 Nov 20269 min readBy Fauzan Ghiffari
A table in a site office with loose papers held down by a stone and a white hard hat next to them
Red flags10to fix before signing
Attach to the contract3drawings, BoQ, specs
Retention≈ 5 %held until defects are fixed
Languages2Indonesian + English

Retention: a typical example for private villa contracts, not a rule. Language: see Law 24/2009, linked in section 07. This guide is general information, not legal advice.

01

Why the contract matters more than the price

Most building disputes in Bali don't start on site. They start months earlier, in a contract that nobody read slowly.

The typical construction contract that Bali builders offer is a short document. Sometimes it is a few pages, a total price and a payment list. It also leaves almost every hard question open: what exactly is included, what happens when it rains for three weeks, and who fixes the crack that appears after handover.

They come back later, when money is paid and changing builder is expensive. The time to close them is before you sign, while both sides still want the deal.

This guide lists ten red flags we see in contracts that owners bring to us, and how to fix each one. Before you sign, have a notary or a lawyer who works in Indonesian construction review the final text.

The short version

A cheap contract is not the one with the lowest price. It is the one with the fewest open questions.

So what does an open question look like on paper? Here are the ten that come up most.

02

Ten red flags at a glance

Read your draft with this list next to it.

  1. A vague scope. "Build a 3-bedroom villa" with no list of what is in and what is out.
  2. No drawings or BoQ attached. The price refers to documents that are not part of the contract.
  3. Front-loaded payments. Most of the money is due before the walls are up.
  4. No retention. Nothing is held back once the keys are handed over.
  5. No defects period. No set time in which the builder must come back and fix things.
  6. Open-ended variations. Changes can be priced after the work is done.
  7. No delay clause. A finish date with no consequence if it is missed.
  8. "Or equivalent" materials. Brands and grades can be swapped without your approval.
  9. Silence on permits and utilities. Nobody is named for the building approval, power or water.
  10. No dispute or language clause. English only, and no agreed way to settle a disagreement.

The first three flags are about one thing: what you are actually buying.

03

Scope, drawings and the BoQ

The scope is the list of work the price covers. If it is vague, every gap becomes an "extra" later. Pools, boundary walls, septic tanks, landscaping, kitchen joinery, air conditioning and site clearing are the usual gaps.

The fix is to attach three documents and say in the contract that they are part of it: the full drawing set, the bill of quantities (BoQ: the itemised list of every material and job, with quantities and unit prices) and the specifications. A price that only refers to "the design" can mean anything later.

Specifications matter more than most owners think. The phrase "or equivalent" lets a builder swap a named tile, tap or roof sheet for a cheaper one. The table shows common wording and what to ask for instead.

Risky wordingWhy it hurtsAsk for instead
"Build villa as per design"No list of what is in or outDrawings, BoQ and specs attached and signed as part of the contract
"Tiles or equivalent"The builder decides what "equivalent" meansBrand, type and grade named; any swap approved by you in writing
"Excluding unforeseen works"Rock, soft soil or old foundations become open-ended extrasUnit rates in the BoQ for digging, rock and fill, used for any extra
"Provisional sum: Rp …"A placeholder that can growA list of what each provisional sum covers, and who approves spending it
"Price includes all works"Sounds complete, proves nothingAn exclusions list: what the price does not cover

Common examples we see in draft contracts. Wording varies; read every clause that limits what the price covers.

Many owners start by searching "construction contract Bali" for a template. A template is a starting point; the clauses in this guide are what to change in it before anyone signs.

Once you know what you are buying, the next question is when you pay for it.

04

How the money moves

The chart compares two example schedules. The dashed line is "paid equals built". Any time a line sits above it, you have paid for work that does not exist yet.

Illustration with example numbers, not a standard schedule. Real splits and stages differ by project.

A deposit is normal. The problem starts when the payments race ahead of the work. If the builder slows down or walks away at point A, most of your money is gone and most of the villa is not.

The fix: tie every payment to a stage you can check on site, such as "structure complete" or "roof closed", and write who confirms that the stage is done. Our guide on how to build a villa in Bali shows a typical stage-by-stage schedule.

Retention. The last few percent, often around 5 %, is held back after handover until the defects period ends. It is the reason a builder comes back to fix a leak. A contract without retention asks you to rely on goodwill alone.

Payments assume the work moves on time. In Bali, that is a big assumption.

05

Delays and changes

Two clauses decide most arguments during a build: what happens when the work runs late, and what happens when something changes.

Delays. A useful delay clause says three things. First, what counts as an allowed delay: heavy rain, a permit hold-up, a change you asked for. Second, how the builder must tell you about it, in writing and within a set number of days. Third, what happens if the delay is the builder's own fault, often a small penalty per day or week, with a cap.

A penalty that is too harsh pushes builders to hide problems or rush the concrete. The aim is honesty about time, not punishment.

Variations. Every build has changes. You move a window. The builder finds rock where the drawings show soil. These changes are called variations. The red flag is a contract that lets them be priced after the work is done.

The fix is simple to write down. No variation starts until the price and the extra time are agreed in writing, by both sides. Prices use the unit rates in the BoQ where they exist. A change agreed only in a WhatsApp voice note is a dispute waiting to happen.

Building materials stacked on a construction site under a blue tarp, with rain falling and puddles on the ground
Write it down

Rain is not a surprise in Bali. It belongs in the contract.

Agree how wet-season days are counted before work starts. Then a three-week downpour is a known allowance, not an argument.

Then comes the day you get the keys. That is where many contracts simply stop.

06

Handover and defects

Handover should be a process, not a date. A good contract describes it: a joint walk-through, a written list of defects (the snag list), a deadline to fix them, and only then the handover payment.

After that comes the defects period. This is a set time after handover, often three to six months for private villas, in which the builder must come back and repair faults at their own cost. Leaks, cracked tiles, doors that stick in the wet season and drains that back up usually appear in this window. The retention is released when it ends and the list is closed.

Indonesia's Construction Services Law (Law No. 2 of 2017) lists items a construction contract should cover, including the maintenance period and building failure with its period of liability. The law has since been amended, so ask your notary or lawyer how the current rules apply to a private villa.

Ask for one more thing at handover: as-built drawings showing where the pipes and cables really run. Without them, every future repair starts with a hammer.

A corrugated zinc-sheet fence around a building site with a closed metal gate
Before the gate opens

The handover payment should follow the snag list, not the calendar.

Walk every room with the builder, write each defect down with a photo, and agree a date to fix it. Pay the handover stage when the list is closed.

Three clauses are left. They look like paperwork, and they cause some of the worst fights.

07

Permits, utilities, language and disputes

Permits and utilities. The building approval (PBG), the power connection and the water supply all take time and money. If the contract doesn't say who arranges and pays for each, assume you will. Name each item: who applies, who pays the fees, and whether the timeline depends on it. Do the same for site costs: temporary power, water for the works, security and waste removal.

Language. Indonesia's language law (Law No. 24 of 2009, Article 31) requires Indonesian in agreements involving Indonesian parties, and allows a second language next to it. In a well-known case, Indonesian courts declared an English-only loan agreement void, as reported by Jones Day. The common practice is a bilingual contract, with a clause that says which version wins if they differ. Read the Indonesian side too, or have it read for you.

Disputes. Agree now how a disagreement will be settled: first a meeting, then mediation, then arbitration or a named court. A contract that is silent here leaves you to work it out under stress, often from abroad.

Worth knowing

Not a legal checklist. Have a notary or a lawyer who knows Indonesian construction read the final version before you sign.

So what does a contract look like when all ten flags are fixed?

08

What a fair contract looks like

A fair construction contract in Bali protects both sides. The builder gets paid on time for real work. You get a villa that matches the drawings, with a way back if it doesn't.

  1. 1

    The documents are part of it

    Drawings, BoQ and specifications are attached, signed and listed by name and date, with a clear exclusions list.

  2. 2

    Money follows the work

    Each payment is tied to a stage you can check on site, and a retention is held until the defects period ends.

  3. 3

    Time and changes are written down

    Allowed delays, notice periods and a fair penalty are defined. No variation starts without a written price and time.

  4. 4

    The end is described

    A snag list, a defects period, as-built drawings and the release of retention, in that order.

  5. 5

    Nothing is left to assume

    Permits, utilities and site costs have an owner. The contract is bilingual and says how disputes are settled.

Before you sign, check these last points yourself:

  • Every page of the drawings and BoQ is initialled by both sides.
  • The total price matches the BoQ total.
  • The finish date and the defects period are written as dates or months, not "approximately".
  • A notary or lawyer has read the final Indonesian and English versions.

If you searched for "construction contract Bali" checklists, this is the short version: attach the drawings and the item list, pay by stage, keep a retention and write down how changes are priced.

How we work

Most of these flags come from a brief and drawings that were never finished. That is why every Xabier project starts with a Brief Review: in one week we test your plot and wishes and give you the result in writing. Then the same team draws, prices and builds it, so the contract can point to documents that are complete.

09

Questions owners ask

What are the 5 elements of a construction contract?

A useful way to think about it: who the parties are, what the work is (scope, drawings and specifications), the price and how it is paid, the time to finish, and what happens when things go wrong (changes, delays, defects and disputes). In Indonesia, Law No. 2 of 2017 on Construction Services lists the items a construction contract should cover. Have a notary or lawyer check your draft against the current rules.

What are the four types of construction contracts?

The common types are lump sum (one fixed price for a defined scope), unit price (you pay measured quantities at agreed rates), cost plus (actual cost plus a fee) and design and build (one party designs and builds). Many villa contracts in Bali are lump sum with a BoQ attached, so extras can be priced at the same unit rates.

What not to tell a contractor?

Avoid saying your budget is flexible, that you are in a hurry, or that the details can be sorted out on site. Each one invites a higher price or an open scope. Share your drawings, your scope and your timeline in writing instead, and let them price exactly that.

Does a construction contract in Bali need to be in Indonesian?

Law No. 24 of 2009 requires Indonesian in agreements involving Indonesian parties and allows a second language next to it. Courts have voided at least one English-only agreement, so a bilingual contract that says which version wins is the common practice. Ask a notary or lawyer to confirm for your case.

Fauzan Ghiffari
Written byFauzan GhiffariFounder, XabierAbout the studio →